Increasing profitability by converting Billing loss into profit

During the scheduling and scoping of a Time and Material (T&M) testing project, considering the leaves and holiday plans, at first place it is not unusual that the Managers think to negotiate the testing scope. Revising scope is necessary to ensure the closing the testing before the Release date communicated by stakeholders. However, this would let some bugs escaping to the Production. Another plan is to put extra efforts to ensure we cover planned testing before release date without compromising. However these extra efforts usually end up in discounts and converted to billing loss.

Usually a team member is supposed to work 8.5 hours a day. Hence a billing cap i.e. maximum billable hours = 8.5 x working days in the month, for a team member. Assume if there are 22 working days, then billing cap will be 187 hours.

Consider a project which starts in January and its first phase will be rolled out in March end. A team member “X” has two planned leaves in the last week of February. As it happens in the projects that more efforts are put in the later phases of the project, to ensure the timely release member “X” also puts extra efforts in month of March i.e. he puts 16 hours of efforts extra.

X has put in 187, 170, and 204 hours in January, February, and March respectively. So there is a billing loss of 16 hours in February and there is a discount of 17 hours to client. However Clients does not prefer to have such discounts as major efforts in the last moment may bring uncertainty and anxiety.

In another similar case, member “Y” has also planned leaves in last week of February. He started putting extra efforts as per his comfort, from the first week of February and adds 16 hours of extra efforts in the month February. In other words the extra efforts “Y” would have to put in March, he put in February.

Y has put in 187, 187, and 187 hours in January, February, and March respectively. He saved 16 hours of billing loss in February. Client is also happy as he got rid of last moment surprises. In cases of adhoc leaves, if possible “Y” should put extra efforts in the current month to reduce the billing loss.

Usually every team member gets >18 holidays in a year. With better leave and efforts planning, if you could save 5 days billing loss per person a year i.e. 42.5 hours per person a year then number multiply by the size of team, will make a considerable impact on profitability. By the same time, team will be able to deliver to the customer as per the agreed plans.

Image

This concept of saving is also applicable in Non T&M projects. Here the target is to identify and plan the Extra Effort to be invested to ensure the Productivity, Quality deliveries, Maximum value for the money to the customer, Minimum billing loss and increase the Profitability of team/company.

I advise that

  1. Customers should be aligned on this model.
  2. Teams should also get the share of this profit.
  3. Teams should be educated and enrolled to understand this model.
  4. Teams should not be denied leaves.
  5. Teams need to plan their leaves in advance though they can take leave on demand.

I never recommend reducing the billing loss by hiding the leaves of the team members. It is better to lose the profit than trust and credibility. . What are your views on this? Do share your experience.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s